| New Construction |
| Phase I: Layout, Lot Preparation, and Permits |
| The first step is to "mark off" your pool as per the layout drawing of your backyard. Let us know immediately if the pool is NOT positioned as you desire. Any lot preparation and tree removal should be completed.Tuxedo will also apply for all the government permits to insure your pool is built in full compliance of building codes. |
|
Excavation
This is the day you've waited for! Pool excavation requires heavy machinery and a dump truck to remove any dirt not needed around the pool. We will do everything possible to keep the mess to a minimum. It is possible that we may encounter unusual conditions, such as rock, collapsible soil, or high water table conditions. In such instances, we'll need to meet with you and discuss the best option, which is likely to add cost to the job. |
|
| Steel & Pre-Plumbing A crew will set and tie a network of steel reinforcing bars to conform to the shape and contour of your pool.Plumbing and lighting fixtures that will be built into your pool will be installed. An inspection by local code inspector must now be made, if required. |
| |
|
Gunite Application
Guniting requires large equipment, so be prepared for a concrete truck and some other machinery. This is an exciting process to watch, but be prepared for lots of dust in the air and the noise of a diesel compressor. Our skilled craftsmen will apply the gunite over the steel to form a single piece gunite shell that will provide the structural strength for you pool...a structure that will endure a lifetime! The crew will trim out the final shape of the pool and "cut-in" such features as steps & benches. |
| |
| Phase II: Tile and Coping Installation |
|
Our tile installers will now arrive and begin to set the tile that
YOU have personally selected around the water line perimeter of the pool. The coping that you have selected will also be installed, giving your pool an attractive, safe and durable edge. In the construction of each pool we strive to make the project everything you dreamed it would be. |
Plumbing A crew will dig trenches for the circulation piping system and install the multiple plumbing lines that run between the pool and the filter system. The plumbing system will be pressure tested and inspected. |
|
|
Install Filtration Equipment Your pump and filter system will now be set in place and connected to the plumbing. Other equipment included in your contract, such as polaris, automatic cleaner, and heater are also installed at this time.If your pool has a heater, a gas line form your gas meter must also be installed and inspected. We can coordinate with the sub-contractor if this is not part of the contract and you will pay him direct or we can do it for you. |
| |
| Phase III: Electrical Rough-in, Bonding and Inspection |
An electrician will install the electrical for the underwater light and provide a safety bonding around the pool. A government electrical inspector must inspect prior to concrete decking being poured.
|
| Install Decking Form Boards If you have chosen concrete decking, we will now form it up. If you want to alter your deck from the original plan, please contact the Construction Coordinator BEFORE the form boards are installed. We can meet with you, revise the plan and advise you of any additional costs. Be sure you are satisfied with the layout of the decking BEFORE the concrete is poured. Adequate expansion joints or saw cuts are installed to help prevent "cracking and chipping" of the concrete as it ages. Be sure NO ONE walks or touches the deck until it has cured for 24 hours. |
| |
| We will prepare your pool for the final finish by pumping out accumulated rainwater and cleaning out construction debris. All pipe and electrical fitting will be grouted and the tile cleaned. |
| |
| We will now plaster or PebbleTec your new pool. When completed, we'll begin filling your pool with water. During this important time, we will need your help. We will need you to watch the water level and turn it off when it reaches the midway point of the skimmer opening. Then call us so we can schedule to start up your system. Please don't let anyone attempt to get in the pool until we say it is okay. |
| |
| Start Up Filtration Equipment After the pool is full, we will return within a couple of days, install your automatic cleaner, and start up your pool pump and filtration system and balance all necessary chemicals. We'll inspect the system for proper operation and be sure everything is performing its best. |
| |
Final Inspections We will arrange for final inspections by your local building officials. With their approval, you can now JUMP IN and begin to enjoy your pool. Instruction Session for Pool Care and Operation One of our experienced staff will meet with you and give you personal instructions on how to care for and operate your pool. At this time you may choose to maintain your pool yourself or have Tuxedo Pools maintain it for you. |
|